Addressing challenges such as extended cable lengths
numerous cables
and diverse cable types of electrical systems for split launching of shield tunneling machines
this paper thoroughly analyzes critical difficulties in the electrical system during split launching and takes a series of targeted solutions. By cataloging the quantity
length
specifications and model of extension cables
conducting insulation performance tests on signal cables of various models and functions
diagnosing short circuits and open circuits
laying and installing extension cables
and performing electrical system commissioning and troubleshooting
this study establishes a framework for electrical system installation
commissioning
and fault resolution under split launching conditions. These measures have demonstrated controllable costs and low failure rates during project implementation
providing reference and inspiration for similar split launching of shield tunneling projects.